Thread
: [Solved]
Task not rolling up after single task was baselined
View Single Post
06-05-2013, 03:43 PM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Sorry, I don't understand.
What
baseline%
are you referring to?
There are the following baselines fields:
Baseline Start
Baseline Finish
Baseline Work
Baseline Duration
Baseline Costs
The is no Baseline % field.
JulieS
View Public Profile
Find all posts by JulieS