Task not rolling up after single task was baselined
I added a single task to my schedule. I set my baseline with the selected task. However the task does not role up to any of the summary tasks.
Under the set baseline options I have tried both Roll up baseline: options but no combination of the options resulted in the baseline % changing..
|