Default Group by Baseline month view - Incorrect task grouping

Greetings!

This has reference to the different post : http://answers.microsoft.com/en-us/office/forum/office_2007-project/task-report-monthly-grouping-by-baseline-x-finish/d25da9b2-a0e2-49e0-b12e-198bb7282fdf

I just thought of creating a new post to track this as a new qusetion.

Background:

I had created a new view to Group tasks by Month & Year, by Grouping on Custom fields based on Baseline Dates of the tasks.
(Custom Month through : Text1=Month([Baseline X Finish]). This logic worked fine for grouping of tasks through 2012.

Now for some of the tasks with the April 2013 Baseline dates, tasks are getting Grouped under Group 5 (Month May 2013) instead of Group 4 (for April 2013).

Just an fyi - I recently moved to MSProject 2010 and also tested Baseline 1 Estimated Finish logic. Unfortunately, the same issue.

Any advise on what could be going wrong?

Thank you in advance for your help!