Thread
:
Exporting/printing MS Project File containing Gantt Chart to an Image
View Single Post
03-19-2013, 05:35 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I understand - but I do want to point out that by using Edays you are counting calendar days - including Weekends - so your overall duration from beginning to end is shorter than it really will be - assuming your resources won't work weekends.
JulieS
View Public Profile
Find all posts by JulieS