Use VBA to create Hammock Tasks
Hi
Wondered if anyone has any idea on how to programmatically create a link from one task start or end date to another, therein allowing me to create a hammock task,
To do this manually, you would select the start date, click copy, select start date if task to be hammocked, click paste special, Paste Link and OK.
Cheers
|