Hello Hugh,
I can confirm I see the same issue. I'm guessing you have different coding for the summary tasks and their subtasks - so using the summary tasks in the group is not correct?
It appears as though the group lines cannot not be used to calculate the correct duration. i have tried with a custom Duration field but the summary task line will not calculate using the formula.
Sorry - I don't know of any work arounds.
|