Hi,
Sorry, there isn't an out of the box report with that format. The best I can suggest is to revised the column (field) order in the Resource Usage view (adding the start and finish dates to the left of the Resource name) and then copy/paste into Excel.
You'll need to then copy/paste assignment rows (task names) if the resource is working on the same task for multiple days.
Julie
|