how to calculate backwards from a set finish date
View Single Post
02-07-2013, 06:50 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
On a copy of the schedule, switch specify the Finish date in Project Information.