Default Baseline query

Hi

I have had to add a few new tasks to my baselined schedule. Should I update the current baseline or create a new baseline?

What is the impact on the project statistics which I am reporting weekly when doing either of the above? Should I just expect to see the difference in the current and baselined work which should equate to the number of work hours added in the new tasks? Just trying to figure out what impact this will have on my reporting.

Thanks for your help

Jo