Thread: [Solved] Assigning Resources to Tasks
View Single Post
 
Old 01-17-2013, 05:18 PM
rickw262 rickw262 is offline Windows XP Office 2010 32bit
Novice
 
Join Date: Jan 2013
Posts: 1
rickw262 is on a distinguished road
Default Assigning Resources to Tasks

Having a very difficult time figuring this out.

Scenario - Project 2010

Create a task that has a DURATION of 20 days and WORK of 40 hours. This means I expect 10 hours of work to be done per week. I assign two resources. One at 25% and one at 75%. When I view the Resource Usage sheet I expect to see 2.5 hours per week for resource 1 and 7.5 hours per week for resource 2. THe Resource Sheet does not show this at all. It seems to screw it up all the time.

Am I even setting this up right?

There will be several tasks that will have work hours set over a longer duration with multiple resources at various percentages so I have to get this right.

Thanks!

Rick
Reply With Quote