Thread
: [Solved]
Summary Report for Individual Task
View Single Post
01-11-2013, 06:33 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I suggest setting up a table with the required fields (resource names, costs) and then filtering all other tasks out. You could add one of the spare flag fields (flag1) set the value in the flag field to "yes" and then filter on that field.
JulieS
View Public Profile
Find all posts by JulieS