It depends upon what you are trying to accomplish - if you don't intend to assign resources, you could use elapsed duration - for example 2emo in the duration field will give you 60 calendar days including non-working days.

The trouble is if you assign resources, they will be assigned for 24 hours per day for the elapsed day duration - so your work values will be wildly inflated.