- Select the tasks.
- Click the Assign resources button to show the assign resources dialog.
- Select the resource who is currently assigned.
- Click the Replace button to show the Replace Resource dialog.
- Select the replacement resource.
- Click OK to close the Replace Resource dialog.
- Click Close to close the Assign Resource dialog.
|