View Single Post
 
Old 12-03-2012, 07:18 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi seanpears99,

No, sorry. No combination of task type is going to allow you to chance dates manually and increase duration. When you manually enter a finish date, Project sets a FNET (finish no earlier than) constraint, maintains the duration, and moves the start date.

The only work around would be to set the task at a low level (1%) complete which sets an Actual Start date. If you then change finish date, the start date will not move.
Reply With Quote