View Single Post
 
Old 11-13-2012, 07:34 PM
Alka Alka is offline Windows XP Office 2010 32bit
Novice
 
Join Date: Nov 2012
Posts: 1
Alka is on a distinguished road
Question Project baseline duration

I have inherited this MS Project schedule. It had baseline but ,since I had to make lot of changes to schedule and add new activities, the baseline was not showing correctly. I have updated baseline where it was missing but now the baseline durations are not showing right. Is there a way to update baseline duration in line with Baseline start and finish dates?
Reply With Quote