Thread: [Solved] Resource Allocation
View Single Post
 
Old 10-02-2012, 02:58 PM
OTPM OTPM is offline Windows 7 32bit Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Julie
I really appreciate your response, especially this late at night .
I am not confusing duration with work. My technical team advise that a task will take two days of effort to complete a task. As such I enter 2 days as the duration. I then assign a resource who is only available for 50% of the time. In which case the task will actually take 4 days to complete in reality.
To give a little more background to my issue:
I have a team that provides both Operational Support and Project Support. These are split as 50% Operational Support and 50% Project Support.
Hope this makes my issue a little clearer.
Kind regards
Tony
Reply With Quote