Hi,
The duration column reflects the elapsed time of tasks but I want to look at the man days required to achieve the task (or tasks). For example I have a plan where the elapsed time for a bunch of tasks is 25 days but the total man days to do the tasks is 94 days. I want to be able to see a column which displays the 94 days.

Can anybody advise which column looks at this.

Many thanks for any help.

Cheers
John