View Single Post
 
Old 08-24-2012, 05:59 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

How can you be 40% complete last week and still 40% complete this week? If you worked on it then the % complete should be increasing unless you have also increased the estimated remaining duration. If you haven't work on it since last week - then the task should be split.

In my opinion, no, you shouldn't be able to have 40% complete for several weeks running without either a split to show that you haven't worked on the task, or an increase in duration to show that you have worked on the task but you underestimated the initial duration.
Reply With Quote