critical path starting in future
Hello,
On my project when I was updating I discovered that the critical path is starting at a future date, although from now till that future date I also have many activities including the first critical activity's predecessors. Why dont I have any critical activities between now and till that future activity? Isnt critical path supposed to encompass the entire duration of the schedule?
|