Push data automatically from Acess or Excel to create a Gantt chart in Project
Hi Everyone
I am new to MS Project. I am trying to use project to create gantt charts of a process that has already occured. I have my data in Access and I want to plot it in Project. Project doesnt support data to be sent form acesss, so i m pushing it to excel and then importing it to project.
Is there any way that i can automate this process and open project from Access?
Also, how do I change the default calender in project to 24hrs as some of my operations are outside of the 8am-5m calender ?
Any help on these topics would be greatly appreciated!!
|