I don't believe there are any filters that will accomplish this. However, if you are using project 2010 you can "walk back" from predecessor to predecessor using the Task Inspector.
I think you need to set predecessors as dictated by the tasks in your project. If it is in a series, link it in a series.
I hope this helps.
Julie
|