Post Filter indirect dependencies

Hi,
Is there a way to filter out tasks that are linked to one specific task (task A, ID 1) indirectly?
I know how to filter out all tasks with lets say task A as predecessor.
But if task C has task B as predecessor which in turn has task A as predecessor I will not found task C when I filter out tasks which has A as predecessor even though task C has task A as predecessor indirctly.

Or should I avoid indirect dependencies and link all tasks to root task?