Hello Katy I,

I'm sorry, but I don't think I understand what you are asking. If you mean have the resource scheduled to work different days on a multi-day task, why?

If the resources has non-working time in their calendar, the task should automatically only schedule working for working days.

You can modify when a resource works on a task through the Task Usage view -- go in and edit the working hours and place the hours where you want them to be.

Is that what you mean?

Julie