Yes, those would be the overallocation days. If they are few and far between, I wouldn't worry about it. Project has to schedule the tasks in a mathematical fashion -- as project managers rarely can we control resources in that manner.
I'd leave the leveling set to week by week but review to make sure everything is okay.
|