Hi Julie
Thank you for your kind help. I know Excel, Word, and PowerPoint but I'm very new to Project.
Task 9 lasts 3 days, and I have up to 60 days, starting from the end of task 4 to complete it. "Fin Plazo" means "Deadline".
I think I will use hard-set dates and "Move project".
Thanks!
|