View Single Post
 
Old 05-25-2012, 07:45 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

From help:
------------------------------------------------
Percent complete:

The % Complete field contains the current status of a task, expressed as the percentage of the task's duration that has been completed.

% Complete = (Actual Duration/Duration) * 100

Physical % Complete:
The Physical % Complete field shows an entered percent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).
-------------------------------------------
The primary purpose of physical % complete is the different method of calculating earned value.
Reply With Quote