From help:
------------------------------------------------
Percent complete:
The % Complete field contains the current status of a task, expressed as the percentage of the task's duration that has been completed.
% Complete = (Actual Duration/Duration) * 100
Physical % Complete:
The Physical % Complete field shows an entered percent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).
-------------------------------------------
The primary purpose of physical % complete is the different method of calculating earned value.
|