changing calendar vs duration
In my schedule there were unstarted activities with certain durations based on 5 day regualr calendar.
When I changed my calendar to a 6 day working calendar, those durations remained the same but the finish dates got sooner now. Why did the duration remain the same? How can i make duratino to update automatically when i change from 5 day calendar to 6 day calendar?
|