You can select which baseline to calculate Variance from in File > Options, Advanced - Earned Value Options (Project 2010) or Tools > Options, Calculation, Earned Value button (2007 or 2003).
You may also calculate Variance manually in spare Duration field. Use the formula:
ProjDateDiff([Baseline1 Finish],[Finish])
to calculate the finish variance using Baseline1 Finish.
I hope this helps.
Julie
|