I don't see a "Project Costs" report -- is this a custom report? I see the following Visual Reports:
Baseline Cost report
Cash Flow report
Resource Cost reports

The baseline cost report relies upon assignments as does the Resource cost report. However, the Cash Flow report can use Fixed costs against tasks without assignments.

So, have you used Fixed Costs against tasks?