View Single Post
04-25-2012, 05:26 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Apply the Resource Usage view and zero out the work for the conflicting task assignment on the meeting day.
I hope this helps.