Julie,

Helpful advice -thankyou.

Ok, so I thought about your suggestion i.e. to not have a master project and now I can see that it is possible to see resouce allocation across all projects from within a single project (as in my case they share the same resource pool).

So the exam question is what key benefits does the master project approach give you over the separate project approach ?

I hope that this will help others in a similar situation.