Hi,
Duration is always the measure of working time and the standard definition (File > Options, Schedule) of a "month" in Project is 20 working days.
To change so the summary tasks show "mon" File > Options, Schedule - Duration is entered in - change from days to months.
That being said -- I wouldn't :-)
|