Sorry, no. The Task Inspector in Project 2010 allows you to jump to a task's predecessor but not successor.

You may view predecessor and successor information including task name by formatting the task form (View > Details) or may like the Relationship Diagram in the lower pane -- but you cannot "walk" through successors, only predecessors.

I hope this helps.