baseline duration, start and finsih dates
View Single Post
04-09-2012, 09:47 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
It sounds as though he may have just copied and pasted the duration to the baseline duration. When a baseline is saved automatically saved are:
Baseline Start
Baseline Finish
Baseline Duration
Baseline Cost
Baseline Work