Linking predecessor twice
View Single Post
04-06-2012, 08:49 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm afraid that is not possible in Project. Consider breaking the placing of the steel into two tasks -- those that can happen concurrently with Forms and then a separate tasks for those placements that require the forms to be finished.
Julie