Hi,
I am displaying task information in each resource in the team planner view. If i double click on each resource name I can go in and assign a calendar to show the shifts associated with that resource. I have 100's of resources so I would like a quicker way of doing this? Is there a table where I can do this? I see that a column option exists for task calendar in the gant chart information field but there is no option for resource calendar?