Thread: [Solved] Legend in MS Project footer
View Single Post
 
Old 03-29-2012, 01:57 PM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Antares,

The only bars which show in the legend are those defined in the Bar Styles dialog. Choose Format, Bar Styles. Copy and existing bar, rename it and change the color. The trick is going to be to get it to only show up for Tasks with Resource A.

See the following link to get you started with creating bars styles for specific resources - See FAQ 31:
http://project.mvps.org/faqs.htm

Although the FAQ references Project 2000, it still applies to Project 2007.
Reply With Quote