Hello Quinton,
The data that appears in the pivot table field list are timescaled values such as Work, Baseline Work, Actual Work, etc.
The fields you have selected: Start, Baseline Start, Finish etc are not timescaled -- they are properties of the task and cannot be added to the timescaled portion of the pivot table. You can right click on any task and select "Show properties in Report" to add the values to the left side of the pivot table.
I hope this helps.
Julie
|