View Single Post
 
Old 03-07-2012, 05:14 AM
Moe Szylak Moe Szylak is offline Windows XP Office 2000
Novice
 
Join Date: Mar 2012
Posts: 1
Moe Szylak is on a distinguished road
Default How to get project to automatically pull in task dates?

I have about 30 tasks split evenly between 2 resources. Each resource has 15 tasks and all subsequent tasks for each individual are to start immediately following completion of the previous task:

I.E.

Task 1 Start: 3/5/12 Finish: 3/7/12
Task 2 Start: 3/8/12 Finish: 3/10/12 Predecessor: Task 1
Task 3 Start: 3/11/12 Finish: 3/13/12 Predecessor: Task 2
and so on.

Say task 1 finishes early, and I change the finish date to 3/6. How do I get project to automatically pull in the dates of tasks 2 and 3 to coincide with task 1 finishing early?

Windows XP, MS Project 2000.

Any help would be greatly appreciated!
Reply With Quote