View Single Post
 
Old 02-29-2012, 06:44 AM
ketanco ketanco is offline Windows 7 64bit Office 2007
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default calculation of start date

Hello,
ALthough I assigned two more predecessors to an activity, which is supposed to delay it further as they finish later, the activitys start date did not change. Why might that be?

After that, since it didnt work, I also tried to force a start date however now it is not changing it to the date i am entering. i tried every way of entering. and while it doesnt change it to the date i like, it doesnt give an error either. it just doesnt change the date... which made my schedule 1 year longer !!!

do you think i have issues with my software here and what can be done?
Reply With Quote