Hi JulieS
I am adding overtime work, not actual overtime work in the Resource Usage view. Regular work value comes from the calendar or?
Why and how is it affected by overtime work.. Ok if overtime work does affect regular work, why overtime work decreases regular work.. If regular work was 8 hours, then i add overtime work is 1 hour... regular work should remain the same, no?
|