Thread
:
remaining duration vs finish date
View Single Post
02-17-2012, 02:24 PM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If the work took longer than originally planned, you should record Actual Duration and then increase remaining duration.