Hello I am facing difficulties figuring out how to use project office. There is supposed to be a class teaching us how to use it in 5 weeks. I can't wait 5 weeks because I got 3 assignments and a dissertation to hand in.
Sorry for sob story.
I have attatched 3 files the image of by node path, the question just in case and the file for office project I have done. I am facing problems in getting the days correctly. I think it should be 455 days. Their are 65 weeks in the critical path. I want to mention the duration but while doing that I want the dates to include the weekends. However noone works on the weekends. I set that up put either I can't count or intel needs to work on thier algorithms.
The 1st task 40 days including weekends that is 56 days. So starting from 01/01/2012 when the weekday starts on a sunday. 01/01/12 to 23/02/12 its adding up to 54 instead of 56. Why?

very frustrating