View Single Post
 
Old 02-08-2012, 04:49 PM
ketanco ketanco is offline Windows 7 64bit Office 2007
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
If you look at the Task Usage view, I imagine you will see zero actual work during the splits. This is expected. My guess is they became split when you updated the project plan and moved any remaining work in the future.

You cannot keep the bar continuous as the activity was not worked on during that time.
Ok how can I tell msproject that these activities was worked on during that time? I want those bars continuous.
When I updated the project I didnt know it was going to split the tasks. I thought it was going to extend the length of the task bar. Do I need to move status date back and then do something like that or what can I do?
Reply With Quote