View Single Post
 
Old 02-08-2012, 02:22 PM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you look at the Task Usage view, I imagine you will see zero actual work during the splits. This is expected. My guess is they became split when you updated the project plan and moved any remaining work in the future.

You cannot keep the bar continuous as the activity was not worked on during that time.
Reply With Quote