There are a number of built in reports in Project 2007 available through the Reports menu. The Earned Value over Time visual report may show what you are searching for -- but in order to work with any comparison reports, you first need to have resources with costs assigned to tasks as well as a saved baseline.
Your calculation settings in Tools > Options, Calculation should be automatic. Your resource leveling calculation should be manual, in my opinion.
Julie
|