Today I made a copy from my project.
I set all tasks include task 8 to 0 %
I move the begin of project in may 2009
So the project start in future.
I found that the tasks 19 to 21 all red = critical.
Is there a bug or mistake in the file ?
Jochen
Edit:
Mistake: Have running project from 26.10.2009 to 29.10.2009
It must be 26.10.2008 to to 29.10.2009
Last edited by Jochen; 04-07-2009 at 10:22 AM.
|