Hi Mike,
A couple of options:
  1. Enter the plumbing inspection task ID and the electrical inspection task IDs into the predecessor field for the drywall installation task. Separate the IDs with a comma.
OR


  1. Select plumbing inspection and CTRL + Click drywall install.
  2. Click the Link tasks button.
  3. Select electrical inspection and CTRL + click drywall install.
  4. Click the link tasks button.
I hope this helps.
Julie