Hi Mike,
A couple of options:
- Enter the plumbing inspection task ID and the electrical inspection task IDs into the predecessor field for the drywall installation task. Separate the IDs with a comma.
OR
- Select plumbing inspection and CTRL + Click drywall install.
- Click the Link tasks button.
- Select electrical inspection and CTRL + click drywall install.
- Click the link tasks button.
I hope this helps.
Julie
|