Thread
:
updating status date and actual duration
View Single Post
01-26-2012, 02:23 PM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
After you update all tasks which are in progress with the Actual Start date etc -- you should move any incomplete work forward to the status date through Tools > Tracking Update Project > Reschedule Uncompleted work to start after (Project 2007).
JulieS
View Public Profile