View Single Post
 
Old 01-26-2012, 11:14 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

When you enter an actual duration greater than the original duration, Project assumes you are complete. Enter the actual duration of 53 days (plus or minus as needed) and then add a remaining duration of 14 days to extend the scheduled finish to where needed.

Leave the % complete alone. Project will calculate the % complete based upon the actual and remaining duration.

I hope this helps.
Julie
Reply With Quote